Phase I of the development is designed to provide flexibility in space usage along with the fit out management. The three warehouses, within the development, have a clear floor to ceiling height of approximately 8 metres, with a length of 109 metres and width of 37 metres, to provide a total storage area of 12,000 square metres.
The electricity power supply for the A/C units has been dividend across all three warehousing to service the different tenants' needs as follows:
| Type 1 : 250 m2 |
|
| A/C Provision: |
4 units x 3 tons (storage area) |
| |
2 units x 3 tons (mezzanine area) |
| |
|
| Type 2 : 500 m2 |
|
| A/C Provision: |
2 units x 3 tons (mezzanine area only) |
| |
|
| Type 3 : 1000 m2 |
|
| A/C Provision: |
2 units x 12.5 tons (storage area) |
| |
2 units x 3 tons (mezzanine area) |
| |
|
"Twin Tech" flooring system, is the system being used in all three buildings to provide a higher ended and more defined surface. "Twin Tech" flooring can provide the following:
- Concentrated load: 75 kilo Newton
- Unified Distribution Load: 35 kilo Newton
- Racking Load: 50 kilo Newton
- Mezzanine Load: 170 kilo Newton
The warehouses have also been designed in such a way to provide a more suitable working environment, due to the sandwich panel isolation system on the walls and ceilings.
Additional specifications are:
- Mezzanine provisions
- Toilet and Kitchenette provisions